Changes may be requested by any stakeholder involved with the pr
2023-11-03(高级)信息系统项目管理师
Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .
A.executive IT manager
B.project manger
C.change control board
D.project sponsor
正确答案是C