在项目没有预测备料的情况下,要缩短供货周期,合理可行的方案有_____ If it required to reduce the material supplying cycle in the case of no spare materials forecasting, the reasonable and feasible proposals contain_____

A.尽早给物流提供工程计划,以便合理安排供货。Provide the engineering plan to Logistics as soon as possible, in order to arrange the material supplying reasonably.

B.及时、准确提供工勘 Provide the accurate site survey report in time.

C.尽量使用标配设备和物料 Use standard configured equipment and materials as much as possible.

D.抢占其他项目资源 Occupy other project resources.

E.减少配置及工勘变更 Reduce the alteration of configuration and site survey.

正确答案是ABCE