You are managing an industrial design project. One of your team members comes to you with a suggestion that will let you do more work while at the same time saving the project 15% of the budget. What is the BEST way for you to proceed?
A.Tell the team to make the change because it will deliver more work for less money
B.Refuse to make the change until a change request is documented and change control is performed
C.Refuse to consider the change because it will affect the baseline
D.Do a cost-benefit analysis and then make sure to inform the sponsor that the project scope changed
正确答案是B